Just a quick update on these two projects.
1) Behind the two homes on 39th
The bypass should be completed the week of the 19th… with trees scheduled the week of the 26th
Fencing should be fixed for homeowner the week of the 3rd
2) 301 project – the project is several weeks behind but should wrap up in a couple of weeks. They need to finalize the retention portion of the road drainage. We are looking at min of mid-October for them to finish and replace trees / fence…restore front to original look.