Ok we are assuming that the agreement between the County and the Contractor will get finalized regarding the pipe issue will be completed this week.
Final clearance from FDEP 12-12 with clearance by 12-22
FDOT Stormwater replacement in the R/W 12-8 to 12-22
The final connection and flow to the new line 12/3 – 12/13
Pumps being removed the 3rd week in January
Grouting can start 3rd week in January
Landscaping and fence relocation completed last week of January