Response to Request for Info from Public Works…

Additional US 301 lane closures this week to make final manhole improvements at the manhole that the new sewer which runs parallel to your subdivision ties into. Once these manhole improvements are completed the large by pass pumps behind the Phillips lot will be removed and replaced with smaller pumps which will not have to run all the time or as much as the large pumps. There will be a lot less sewer flow being repumped behind the homes since the new main will be operating and taking all the flow from south and east of the site. The small pumps will be placed as far from the homes as possible. The smaller pumps should be in place by the end of the week.

The contractor will start installing the last few pieces of pipe to connect the new pipe to the old pipe between the two lots. When this is completed and accepted the small pumps will be removed the week of February 13th.

Grouting of existing pipe and manholes to begin the week of February 20th.

Week of February 27th replacement of fence and landscaping behind the lots.

The trees along US 301 should be installed by the end of next week and the FDOT regrading and sidewalk complete by mid February.