Creekside Sewer mtg

Updates:
• 15” line installed/tested
• Landscaper is pricing the adds/change on hedge > install next week; Need to have Chris call his irrigation guys and put them on notice. Landscape can coordinate name and number given so the timing can be nailed down
• PVC fence to follow landscaping the following week
• Underdrain 301 is 90% but things on hold until deflection of water by HMB gets completed (hoping deflection starts Monday); prob two weeks get wrapped up with testing included